Local projects
 
 
 
Taicang Xinwang Energy Co., Ltd. Expansion Project
Steel structure, Floor Area:4,650 sqm
Starting Date: May 2010
Completion Date: July 2010
 
 
 
 
Wanvog Furniture (Kunshan) Plant, Building 6
Frame structure, Floor Area:38,500 sqm
Starting Date: April 2010
Completion Date: November 2010
 
 
 
 
Carpoly Paint (Shanghai) New Plant
Frame structure, Floor Area:28,318 sqm
Starting Date: March 2010
Completion Date: August 2010
 
 
 
 
Manuli Hydraulic Equipment (Suzhou) Co., Ltd. ,Phase VII
Frame structure, Floor Area:6,344 sqm
Starting Date: January 2010
Completion Date: June 2010
 
 
 
 
Synnex Technology International (Hangzhou) Electronics Plant
Frame structure, Floor Area:10,087 sqm
Starting Date: December 2009
Completion Date: August 2010
 
 
 
 
No. 1 Workshop for Thick Double-sided Adhesive Project in Jinshan Factory
Frame structure, Floor Area:3,452 sqm
Starting Date: December 2009
Completion Date: August 2010
 
 
 
 
General Mills (Sanhe) Co., Ltd., Phase 1
Steel structure/Frame structure, Floor Area:6,920 sqm
Starting Date: December 2009
Completion Date: August 2010
 
 
 
 
Tenwow (Fujian) Food Project, Building 1-4
Frame structure, Floor Area:35,000 sqm
Starting Date: December 2009
Completion Date: July 2010
 
 
 
 
Sulzer Pumps Suzhou New Factory Project
RC structure/Steel structure, Floor Area:22,570 sqm
Starting Date: December 2009
Completion Date: July 2010
 
 
 
 
Rich Products Suzhou Co., Ltd. Phase II
RC structure£¬ Floor Area:7,422 sqm
Starting Date: August 2009
Completion Date: December 2009
 
 
 
 
Kailai Apartment
Frame structure£¬ Floor Area:160,000 sqm
Starting Date: June 2009
Completion Date: December 2010
 
 
 
 
Wharf (Holdings) Limited-Times Plaza Block B
Frame structure£¬ Floor Area:140,000 sqm
Starting Date: March 2009
Completion Date: December 2010
 
 
 
 
Yujun (Weifang) New Plant Project
Steel structure/Frame structure, Floor Area:23,500 sqm
Starting Date: March 2009
Completion Date: November 2010
 
 
 
 
Combined Factory Building of IPAGSA Printing Equipment(JX) Co., Ltd.
Steel structure/Frame structure, Floor Area:15,527 sqm
Starting Date: March 2009
Completion Date: December 2009
 
 
 
 
Pilot¡¯s Cabin Production and Assembly Project
RC structure£¬ Floor Area:36,892 sqm
Starting Date: February 2009
Completion Date: October 2009
 
 
 
 
Shengneng Technology (Suzhou) Plant, Phase 1
Light Steel structure, Floor Area:4,550 sqm
Starting Date: November 2008
Completion Date: August 2009
 
 
 
 
Brintons Carpet Manufacturing (Suzhou) New Plant
Steel structure/Frame structure, Floor Area:23,845 sqm
Starting Date: October 2008
Completion Date: April 2009
 
 
 
 
Haimen Doctor Garden
Frame structure£¬ Floor Area:105,000 sqm
Starting Date: August 2008
Completion Date: December 2009
 
 
 
 
Xinxiang General Oxygen-free Copper Products Factory
Steel structure/RC structure£¬ Floor Area:22,000 sqm
Starting Date: August 2008
Completion Date: August 2009
 
 
 
 
Caterpillar (Suzhou) Project
Steel structure,Frame structure, Floor Area:72,913 sqm
Starting Date: June 2008
Completion Date: April 2009
 
 
 
 
RT-Market (Zhejiang) Cixi Market
Frame structure, Floor Area:49,829 sqm
Starting Date: June 2008
Completion Date: March 2009
 
 
 
 
Trina Solar (Changzhou) Project
Frame structure, Floor Area:32,252 sqm
Starting Date: May 2008
Completion Date: May 2010
 
 
 
 
The Civil Project For Building A And B Of L¡¯Or¨¦al (China) R&D Centre Project
Frame structure, Floor Area:15,000 sqm
Starting Date: April 2008
Completion Date: July 2009
 
 
 
 
Jiaxing ICL Co., Ltd., New Plant
Frame structure, Floor Area:14,000 sqm
Starting Date: April 2008
Completion Date: April 2009
 
 
 
 
Wacker Polymer System (Nanjing) Co., Ltd.
Frame structure, Floor Area:11,000 sqm
Starting Date: April 2008
Completion Date: January 2009
 
 
 
 
Federal-Mogul Corporation HQ & Technical Center
RC structure/Steel structure, Floor Area:8,874 sqm
Starting Date: April 2008
Completion Date: November 2008
 
 
 
 
Shanghai-Hong Kong New World Garden
Frame structure, Floor Area:16,000 sqm
Starting Date: March 2008
Completion Date: October 2010
 
 
 
 
Taiwan Chuangxing Precision Chemistry Co., Ltd.
Steel structure, Floor Area:11,586 sqm
Starting Date: January 2008
Completion Date: July 2008
 
 
 
 
Kunjie Electronics (Kunshan) Plant
RC structure/Steel structure, Floor Area:14,090 sqm
Starting Date: November 2007
Completion Date: June 2008
 
 
 
 
Taiwan Dongpei Industry Co., Ltd.
Steel structure, Floor Area:24,099 sqm
Starting Date: November 2007
Completion Date: May 2008
 
 
 
 
Spring Of Shanghai
Frame structure£¬ Floor Area:65,725 sqm
Starting Date: August 2007
Completion Date: August 2008
 
 
 
 
Shanghai Mengli Automatic Technology Co., Ltd.
RC structure/Steel structure, Floor Area:11,024 sqm
Starting Date: July 2007
Completion Date: June 2008
 
 
 
 
BATZ Automotive Systems (Kunshan) New Plant
Frame structure, Floor Area:5,254 sqm
Starting Date: July 2007
Completion Date: March 2008
 
 
 
 
Fagor Catering (Kunshan) New Factory
Steel structure/Frame structure, Floor Area:9,170 sqm
Starting Date: June 2007
Completion Date: April 2008
 
 
 
 
Chiyoda Integre (Suzhou) Co., Ltd., Expansion Project
RC structure£¬ Floor Area:5,000 sqm
Starting Date: January 2007
Completion Date: September 2007
 
 
 
 
Tokico Automotive (Suzhou) Co., Ltd. Expansion project
RC structure/Steel structure, Floor Area:12,000 sqm
Starting Date: December 2006
Completion Date: May 2007
 
 
 
 
RT-Market (Shanghai) Logistic Center Warehouse
Frame structure,, Floor Area:16,289 sqm
Starting Date: November 2006
Completion Date: July 2007
 
 
 
 
Hyundai Shanghai Plaza
Frame structure£¬ Floor Area:69,600 sqm
Starting Date: August 2006
Completion Date: June 2007
 
 
 
 
Concordia International School Shanghai Phase III
Frame structure, Floor Area:10,245 sqm
Starting Date: August 2006
Completion Date: June 2007
 
 
 
 
Heinz Longfong Food (Chengdu) Plant
RC structure/Steel structure, Floor Area:15,000 sqm
Starting Date: August 2006
Completion Date: May 2007
 
 
 
 
CSA Works of Rhodia WRAP Project
RC structure/Steel structure, Floor Area:28,000 sqm
Starting Date: April 2006
Completion Date: May 2007
 
 
 
 
USA. G.M. Food (Shanghai) Plant
RC structure/Steel structure, Floor Area:21,989 sqm
Starting Date: February 2006
Completion Date: October 2006
 
 
 
 
Accuride International Precision Industrial (Suzhou) Plant
RC structure/Steel structure, Floor Area:23,000 sqm
Starting Date: February 2006
Completion Date: August 2006
 
 
 
 
Optibelt Power Transmission (Taicang) Plant
Steel structure, Floor Area:11,800 sqm
Starting Date: December 2005
Completion Date: August 2006
 
 
 
 
AKG New Plant, Taicang, Phase 2
Steel structure, Floor Area:5,000 sqm
Starting Date: August 2005
Completion Date: March 2006
 
 
 
 
Yageo Electronics (Suzhou) Plant II
Frame structure, Floor Area:36,000 sqm
Starting Date: June 2005
Completion Date: December 2006
 
 
 
 
HITACHI Cable (Suzhou) Plant
Frame structure, Floor Area:7,800 sqm
Starting Date: May 2005
Completion Date: November 2005
 
 
 
 
Plantronics Suzhou Project
RC structure/Steel structure, Floor Area:21,550 sqm
Starting Date: February 2005
Completion Date: March 2006
 
 
 
 
Suzhou Chuo Malleable (Suzhou) Plant
Frame structure/Light Steel structure, Floor Area:13,138 sqm
Starting Date: December 2004
Completion Date: June 2005
 
 
 
 
Walton Suzhou S2 Plant Turnkey Project
Steel structure/RC structure, Floor Area:36,572 sqm
Starting Date: November 2004
Completion Date: March 2005
 
 
 
 
Block 19, Apartment Wanli
Frame structure£¬ Floor Area:120,000 sqm
Starting Date: October 2004
Completion Date: September 2006
 
 
 
 
BlueScope Steel (Suzhou) Co., Ltd. China Coating Project
Steel structure/RC structure, Floor Area:6,328 sqm
Starting Date: October 2004
Completion Date: June 2006
 
 
 
 
Concordia International School Shanghai Phase II
Frame structure, Floor Area:15,068 sqm
Starting Date: October 2004
Completion Date: October 2005
 
 
 
 
Kangchen Logistic Center Warehouse (Suzhou) Phase I
Steel structure/Frame structure, Floor Area:93,000 sqm
Starting Date: September 2004
Completion Date: February 2005
 
 
 
 
Eagle Ottawa China Ltd., Xin Zhuang Facility
Steel structure, Floor Area:10,526 sqm
Starting Date: August 2004
Completion Date: February 2005
 
 
 
 
USA. 3M Technology (SuZhou) Plant
Steel structure, Floor Area:15,000 sqm
Starting Date: July 2004
Completion Date: March 2005
 
 
 
 
USA. Wanvog Furniture (KunShan) Plant, Phase II
RC structure/Steel structure, Floor Area:55,130 sqm
Starting Date: June 2004
Completion Date: December 2004
 
 
 
 
Sew (Suzhou) Expansion Plant
Steel structure, Floor Area:8,200 sqm
Starting Date: May 2004
Completion Date: September 2004
 
 
 
 
USA. Wanvog Furniture (KunShan) Plant, Phase I
RC structure/Steel structure, Floor Area:39,870 sqm
Starting Date: December 2003
Completion Date: June 2004
 
 
 
 
Nippon Metal Manufacture (Suzhou) Plant
RC structure/Steel structure, Floor Area:10,000 sqm
Starting Date: November 2003
Completion Date: June 2004
 
 
 
 
Shimizu Corporation (Suzhou) Project
Steel structure/RC structure, Floor Area:24,000 sqm
Starting Date: November 2003
Completion Date: May 2004
 
 
 
 
YKKAP Factory Project (Phase One)
RC structure/Steel structure, Floor Area:49,128 sqm
Starting Date: August 2003
Completion Date: February 2004
 
 
 
 
Shanghai PuDong Shangri-la Hotel (Phase 2) Above Ground Structure
Frame structure£¬ Floor Area:50,000 sqm
Starting Date: July 2003
Completion Date: February 2005
 
 
 
 
Maxtor SuZhou) Technology Plant
Frame structure, Floor Area:88,215 sqm
Starting Date: May 2003
Completion Date: February 2004
 
 
 
 
HITACHI Display Su Zhou Plant
Frame structure, Floor Area:28,190 sqm
Starting Date: December 2002
Completion Date: September 2003
 
 
 
 
Nanjing Accurate Electronic Parts Plant
Steel structure/RC structure, Floor Area:4,300 sqm
Starting Date: August 2002
Completion Date: December 2002
 
 
 
 
O¡¯real Cosmetic (Suzhou) Factory
Rebuilding Project,Steel structure, Floor Area:4,400 sqm
Starting Date: January 2002
Completion Date: April 2003
 
 
 
 
American Nabisco Food Suzhou Plant
Steel structure/RC structure, Floor Area:13,000 sqm
Starting Date: December 2001
Completion Date: March 2002
 
 
 
 
Rich Products Su Zhou Plant
Steel structure, Floor Area:4,200 sqm
Starting Date: April 2001
Completion Date: September 2001
 
 
 
 
Bosch Automotive Product (Suzhou) Factory
Steel structure/Frame structure, Floor Area:21,400 sqm
Starting Date: March 2001
Completion Date: December 2001
 
 
 
 
Meilong Town, Phase 1
RC structure£¬ Floor Area:85,840 sqm
Starting Date: February 2000
Completion Date: February 2001
 
 
 
 
General Mill Food (Nanjing) Plant
Steel structure, Floor Area:6,140 sqm
Starting Date: March 1999
Completion Date: November 1999
 
 
 
 
Shanghai Mingshi Garden
Frame structure£¬ Floor Area:57,878 sqm
Starting Date: June 1998
Completion Date: May 1999
 
 
 
 
Kerry Commercial Center
Frame structure£¬ Floor Area:81,986 sqm
Starting Date: July 1996
Completion Date: September 1998
 
 
 
 
Shanghai International Garden
Frame structure£¬ Floor Area:25,127 sqm
Starting Date: March 1994
Completion Date: September 1995
 
 
Projects in singapore
 
 
Altez Residence
General contractor: Woh Hup (Private) Ltd
Floor Area: 60,000 sqm
Structure: 62F
 
 
 
 
The Interlace
General contractor: Woh Hup (Private) Ltd
Floor Area: 170,000 sqm
Structure: 24F+1F Basement£¬ 1040 units
 
 
 
 
Meyer Apartment
General contractor: Woh Hup (Private) Ltd
Floor Area: 60,000 sqm
Structure: 24F+1F Basement,1040 units
Construction duration: October 2008 - September 2009
 
 
 
 
Reflection at Keppel Bay Residence
General contractor: Woh Hup (Private) Ltd
Floor Area: 200,000 sqm
Structure: 41F+2F Basement
Construction duration: July 2008 - July 2010
 
 
 
 
Ocean Financial Center
General contractor: Obayashi Corporation & Woh Hup Pte Ltd
Floor Area: 100,000 sqm
Structure: 43F
Construction duration: May 2008 - May 2010
 
 
 
 
Straits Office Building
General contractor: Obayashi Corporation
Floor Area: 30,000 sqm
Structure: 28F
Construction duration: March 2008 - June 2009
 
 
 
 
Orange Grove
General contractor: KSH Holdings
Floor Area: 130,000 sqm
Structure: 12F+1F Basement,72 units
Construction duration: January 2008 - December 2008
 
 
 
 
Tate Apartment
General contractor: Woh Hup (Private) Ltd
Floor Area: 30,000 sqm
Structure: 36F+1F Basement
Construction duration: December 2007 - July 2009
 
 
 
 
Mi Casa Residence
General contractor: Woh Hup (Private) Ltd
Floor Area: 60,000 sqm
Structure: 7 buildings£¬17F£¬457 units
Construction duration: December 2007 - December 2008
 
 
 
 
Commerce & Finance Center
General contractor: Woh Hup Pte Ltd & Kajima Overseas Asia Pte Ltd
Floor Area: 70,000 sqm/150,000 sqm
Structure: 55F/51F
Construction duration: July 2007 - November 2009/May 2008 - March 2010
 
 
 
 
City Square Shopping Center
General contractor: Kajima Overseas Asia Pte Ltd
Floor Area: 70,000 sqm
Structure: 9F
 
 
 
 
Apartment and Jurong Shopping Center Phase II
General contractor: Woh Hup (Private) Ltd
Floor Area: 250,000 sqm
Structure: 16F+4F Basement
 
 
 
 
Yaleju Apartment
General contractor: Woh Hup (Private) Ltd
Floor Area: 100,000 sqm
Structure: 30F+3F Basement
 
 
 
 
Cappella Hotel
General contractor: Singapore Greatwall Co., Ltd.
Floor Area: 70,000 sqm
Structure: 6F+1F Basement
 
 
 